We are creating projects via Appropriation requests. The theory is that no commitments should be created before the project is released. However, we have proven that users can change the Res./Purc. indicator to 'immediate' before the project has been released. If the approver does not pick up that the project is not released yet, they can even create a Purchase order.
You can not remove authorisation for the "immediate" indicator, because the indicator changes when you release the project from "from release" to "immediate".How can we stop ANY committments from being created until the project has been released?
In OPSC make sure the Release immediately has been unmarked.In transac OPUA (field selection network header) go to influencing choose network profile or controlling area depending on which you want to customize. Set the field "Reservation/Purc.req" CAUFVD-AUDISP make it to only displauy.Go to transac OPUC (field selection network details) go to influencing, choose network profile or contolling area to which you want to customize the setting. Set it to change and in the field "Reservation/Purc.req" - AFVGD-AUDISP make it to only display. This would prevent the users from changing it to display when they create and assign activities to networks/projects.
One more customization, in transac OPUU in the network tab make sure the setting is for 2 (from release)
or
A very effective way to handle this is using User status management .go to tcode bs02 and define a status profile which can be defaulted in the project profile, in the status profile define proj definition,WBS,network header and network activity as the infulenced object types.
Create a status "blck" as an initital status and in the business transaction field block PR and PRQ creation.Next create a status"allw" which will be set after project is released and allow PR and PRQ creation after status is set
Saturday, April 19, 2008
Stop Commitments Before Release Of Projects
Labels:
Logistics Information System
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2008
(88)
-
▼
April
(32)
- How do upgrades work?
- How is the software delivered?
- Is it difficult to install D&B for SAP R/3?
- Didn't D&B compete against SAP, providing client/s...
- What is the price of the D&B data?
- Will the D&B product remain on SAP's global price ...
- Who will provide technical support of the D&B serv...
- Who has access to view D&B information SAP R/3?
- How secure is the existing data in SAP R/3?
- Can the D&B Online Access software be customized?
- What are the technical prerequisites for using D&B...
- What are the benefits in using D&B for SAP Solutio...
- What is Data Rationalization and Online Access?
- Is this partnership a new strategy for D&B and SAP...
- Is this product/service available globally?
- Do you have any customers using the software funct...
- What kinds of companies (markets) are you targetin...
- When will the software component be available to m...
- What is significant about online access in R/3 to ...
- What are the benefits for SAP and D&B?
- Do I have to have mySAP.com to be able to use D&B ...
- What does the inclusion of D&B for SAP R/3 in mySA...
- Is the relationship between D&B and SAP exclusive ...
- Describe the nature of the relationship between SA...
- SAP LIS - Wrong figures in Logistics Information S...
- List of standard Reports in MM
- Project Status set to TECO
- List of RA caculated values
- Stop Commitments Before Release Of Projects
- What is WBS element?
- Aggregate POC Calculation
- Dynamic Selection on Report Not Working
-
▼
April
(32)
No comments:
Post a Comment