When we confirm activities and see it in cns41 report we can see that the POC is aggregated at the Network,WBS and porject level. How does the system calculate this.. i.e on what factors and criteria?
Result analysis determines the costs & revenues belong to the period, along with the Work in progress (WIP) or Reserves.
Result analysis calculation is based on the planned / actual Cost & Revenue.
POC (Percentage of Completion) determines by the valuation method you opt …
The formula for POC :
POC = R (a) / R (P) Revenue Proportionate
POC = C (a) / C (p) Cost Proportionate
Result Analysis Determines:
- Calculated Costs C(c) = POC X C (p) Same for Revenue - WIP (If C(a) >C (c) ) WIP = C(z)= C(a) - C(p)- Reserves for unrealized costs (if C(a) <> R(c) ) R (r) = R(a) –R(c)
E.g.
Revenue Proportionate RA:
In some project you have R(p) =3000$C (p) = 2000$R (a) = 1200$C (a) = 1000$
Then POC = 1200 /3000 = 40 %
C(c) = POC X C(p) = 40 % X 2000 = 800$
WIP = C(z) = C(a) –C(c) = 1000-800 =200$
Saturday, April 19, 2008
Aggregate POC Calculation
Labels:
Logistics Information System
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2008
(88)
-
▼
April
(32)
- How do upgrades work?
- How is the software delivered?
- Is it difficult to install D&B for SAP R/3?
- Didn't D&B compete against SAP, providing client/s...
- What is the price of the D&B data?
- Will the D&B product remain on SAP's global price ...
- Who will provide technical support of the D&B serv...
- Who has access to view D&B information SAP R/3?
- How secure is the existing data in SAP R/3?
- Can the D&B Online Access software be customized?
- What are the technical prerequisites for using D&B...
- What are the benefits in using D&B for SAP Solutio...
- What is Data Rationalization and Online Access?
- Is this partnership a new strategy for D&B and SAP...
- Is this product/service available globally?
- Do you have any customers using the software funct...
- What kinds of companies (markets) are you targetin...
- When will the software component be available to m...
- What is significant about online access in R/3 to ...
- What are the benefits for SAP and D&B?
- Do I have to have mySAP.com to be able to use D&B ...
- What does the inclusion of D&B for SAP R/3 in mySA...
- Is the relationship between D&B and SAP exclusive ...
- Describe the nature of the relationship between SA...
- SAP LIS - Wrong figures in Logistics Information S...
- List of standard Reports in MM
- Project Status set to TECO
- List of RA caculated values
- Stop Commitments Before Release Of Projects
- What is WBS element?
- Aggregate POC Calculation
- Dynamic Selection on Report Not Working
-
▼
April
(32)
No comments:
Post a Comment