When I set a project on status TECO. We can still do confirmations on the project.
Is there a setting or a way in which we can set the project to TECO and not be able to do confirmations on that particular project?
There is no link between TECO and actual confirmation. It might possible that the project is technically completed but non technical activities are still pending..
All WBS elements, networks and activities are set on status TECO in the project. I have set the status over a week ago and yet am still allowed to do confirmations to the activities in the project.
We did not experience this problem before. It is the first time and it happens for all projects that are set to status TECO.
If you have networks and activities involved your best bet is to use project builder to make a status change at the project definition level which will cascade down to wbs elements, network header and network operations.
You may try setting a DLFG flag and see if it prevents confirmations from occurring on the activities. If you need to undo the deletion flag the sequence is as follows:
Using CJ02 undo DLFG at project definition level then select all wbs elements and perform the same. using CN22 undo DLFG at network header level then select all activities and perform the same.
Project builder allows status set downwards but not undo on all components, therefore requiring CJ02 and CN22 to undo.
Saturday, April 19, 2008
Project Status set to TECO
Labels:
Logistics Information System
Subscribe to:
Post Comments (Atom)
Archives
-
▼
2008
(88)
-
▼
April
(32)
- How do upgrades work?
- How is the software delivered?
- Is it difficult to install D&B for SAP R/3?
- Didn't D&B compete against SAP, providing client/s...
- What is the price of the D&B data?
- Will the D&B product remain on SAP's global price ...
- Who will provide technical support of the D&B serv...
- Who has access to view D&B information SAP R/3?
- How secure is the existing data in SAP R/3?
- Can the D&B Online Access software be customized?
- What are the technical prerequisites for using D&B...
- What are the benefits in using D&B for SAP Solutio...
- What is Data Rationalization and Online Access?
- Is this partnership a new strategy for D&B and SAP...
- Is this product/service available globally?
- Do you have any customers using the software funct...
- What kinds of companies (markets) are you targetin...
- When will the software component be available to m...
- What is significant about online access in R/3 to ...
- What are the benefits for SAP and D&B?
- Do I have to have mySAP.com to be able to use D&B ...
- What does the inclusion of D&B for SAP R/3 in mySA...
- Is the relationship between D&B and SAP exclusive ...
- Describe the nature of the relationship between SA...
- SAP LIS - Wrong figures in Logistics Information S...
- List of standard Reports in MM
- Project Status set to TECO
- List of RA caculated values
- Stop Commitments Before Release Of Projects
- What is WBS element?
- Aggregate POC Calculation
- Dynamic Selection on Report Not Working
-
▼
April
(32)
No comments:
Post a Comment